Projects Listed in Order of Construction Sequence
Concrete Streets - Completed
Street | To | From |
Crest Court | Woodbine | Cul-de-sac |
Missouri | Cherry | Westchester Entrance |
Asphalt Streets - Completed
Street | To | From |
W Jewel | N Geyer | Cul-de-sac |
W Washington | N Geyer | N Van Buren Ave |
Pleasant Ct. | W Washington | Cul-de-sac |
W Woodbine | Edna | Dead End |
Barby Ln. | Craig | Cul-de-sac |
Contracts for street resurfacing on the above streets were approved by City Council on April 4, 2024. City Streets were selected by the Engineering Department based on pavement condition, routes to local schools, and amount of traffic. These projects are anticipated to start in early summer and be completed prior to school start in August.
Rejuvenator Streets - Completed
This work shall consist of the application of an emulsified maltene based asphalt rejuvenator to the following Asphalt streets within the City of Kirkwood:
Street |
To |
From |
Jefferson |
Harrison |
Taylor |
Chelsea |
Dickson |
Dickson |
Glendower |
Chelsea |
Chelsea |
Warrenton Dr |
Lewiston |
Lewiston |
Lewiston |
Cul-de-Sac |
Dickson |
Drury Ln |
Cul-de-Sac |
Dickson |
S Taylor Ave |
Woodbine |
Monroe |
Applewood Dr |
Bedford Oaks Dr |
Dougherty Ferry Rd |
Bedford Oaks Dr |
Cul-de-Sac @ N Geyer |
Dougherty Ferry Rd |
Bedford Oaks Dr |
Bedford Oaks Dr |
Applewood Dr |
Bryan Ave |
End of Street |
W Essex Dr |
Colonial Oak Ln |
Cul-de-Sac |
Frances Rd |
Cornhill Ln |
Cul-de-Sac |
Lindeman Rd |
Dougherty Pl |
Second Cul-de-Sac |
Dougherty Ferry Rd |
Iris Ln |
Cul-de-Sac |
W Essex Dr |
Lockett Ln |
Sherlin Dr Cul-de-Sac |
Cul-de-Sac |
Reith Terrace |
Spring House Dr |
Dougherty Ferry Rd |
Sherilin Dr |
Cul-de-Sac |
Cul-de-Sac |
Spring House Dr |
Cul-de-Sac |
Reith Terrace |
Oak Bluff Ln |
Cul-de-Sac |
Frances Rd |
W Essex Ave |
To PCCP |
Dougherty Ferry Rd |
Missouri Ave |
Cherry St |
Manchester Rd |
Lockett Rd |
Des Peres City limits |
Lin Manor Dr |
For project questions on this project, please contact Richard Holesinger, City Engineer, at holesire@kirkwoodmo.org or (314) 822-5819.
Last Updated: November 19, 2024
Project Status: Construction Completed
Improvements have been constructed on Longview Boulevard!
The Longview Boulevard Improvement Project has analyzed and recommended the best location for sidewalks on Longview Boulevard and East Essex Avenue. The project will also include traffic calming, resurfacing and restriping Longview Boulevard.
For more information about the Public Engagement that occurred on this project, please visit: https://www.kirkwoodmo.org/government/making-pedestrian-safety-a-priority.
The preliminary plan public comment period ended on December 9th. The City has completed preliminary and right of way plans and bidding plans is under construction.
The right of way plans can be viewed here.
The bidding/construction plans can be viewed here. These are the latest set of plans.
All necessary easements have been acquired for the project. The project was approved by City Council on October 19, 2023. A resident notification dated November 16, 2023 was sent to adjacent property owners to the project which can be viewed here. The City is under contract with Jokerst Paving to complete the project. Construction on the project started on Monday, December 4th. Completion of the project is expected to occur in early summer 2024.
For project questions on this project, please contact Chris Krueger, Public Services Director, at kruegeca@kirkwoodmo.org or (314) 822-5822.
Last Updated: August 16, 2024
Notification to Residents on the streets affected can be viewed here.
#14076 - 2024 High Build Acrylic Waterborne Pavement Markings |
||
Project Scope: |
This project includes 1. Application of new pavement markings to re-freshen existing striping and pavement markings on various streets. |
|
Limits: |
Various Streets |
|
Length (Mile): |
0.236 |
|
Project Status: |
Under Construction |
October 9, 2024 |
Design Engineering: |
In-House |
|
Contractor: |
TraMar Contracting, Inc. |
|
Project Construction Start: |
October 2024 |
|
Estimated Project Completion: |
January 2025 |
|
Estimate Project Construction cost (Not to Exceed): |
$ 350,274.32 |
Updated: November 19, 2024
#14080 - 2024 Concrete Pavement Joint and Crack Sealing - Out for Bid |
||
Project Scope: |
This project includes: Placement of advance notification signs, temporary traffic control devices, thorough cleaning, removal of waste material, preparation of all cracks and joints in concrete pavements, and along curb lines, between top of curbs and private driveways, to various concrete streets in the City of Kirkwood. The application of polymer-modified crumb rubber hot pour liquid crack sealer will be applied to all cracks and joints one-eight (1/8) of an inch in width or wider. |
|
Limits: |
117 Sites |
|
Length (Mile): |
17.43 |
|
Project Status: |
Bid Opening |
Tuesday, September 24, 2024 |
Design Engineering: |
In-House |
|
Contractor: |
PLM |
|
Project Construction Start: |
December 2024 |
|
Estimated Project Completion: |
February 2025 |
|
Estimate Project Construction cost (Not to Exceed): |
$101,233.44 |
|
Updated: November 19, 2024
#14080 - City-Wide Stormwater Master PlanThe web link to HR Green questionaire can be found here: https://hrgreen.mysocialpinpoint.com/kirkwood-smp/home/The flyer link can be found here: https://www.hrgreen.com/wp-content/uploads/2024/09/City-of-Kirkwood-Stormwater-flyer-091624-3.pdfFirst Open house meeting information can be seen here. |
||
Project Scope: |
This project includes: The City of Kirkwood has identified stormwater problems in yards, streets, and basements involving ponding, flooding, and erosion. Further, the responsibility for stormwater management is divided among several agencies: Metropolitan St. Louis Sewer District (MSD), St. Louis County Highway Department, Missouri Department of Transportation (MoDOT), the City of Kirkwood, and individual property owners. Therefore, the City desires to develop a community-based Stormwater Master Plan that identifies the problems, identifies stormwater projects, prioritizes the projects, and identifies funding sources. |
|
Limits: |
City Wide |
|
Project Status: |
Bid Opening |
Tuesday, September 24, 2024 |
Design Engineering: |
HR Green, Inc. |
|
Estimate Project Construction cost (Not to Exceed): |
$ 173,113.60 |
|
Project Milestone |
Original Deliverable Date |
Proposed Revised Deliverable Date |
Fee Proposal to City for Review |
13-May-24 |
14-Jun-24 |
Council Authorization |
6-Jun-24 |
18-Jul-24 |
Notice to Proceed |
8-Jul-24 |
August 12, 2024 (Kickoff |
August 23, 2024) |
||
Public Outreach Program Development |
July 10, 2024 – July 31, 2024 |
8-Oct-2024 |
22-Oct-24 |
||
GIS-Based Data Collection |
July 10, 2024 – October 8, 2024 |
August 12, 2024 – |
13-Nov-24 |
||
Public Outreach |
July 10, 2024 – September 9, 2024 |
August 23, 2024 – |
25-Oct-24 |
||
Initial Problem Summary + City Review |
October 8, 2024 – October 15, 2024 |
October 25, 2024 – |
1-Nov-24 |
||
Targeted Field Visits |
October 15, 2024 – October 29, 2024 |
November 1, 2024 – |
15-Nov-24 |
||
Prioritization of Needs with City |
October 29, 2024 – November 14, 2024 |
November 15, 2024 – |
27-Nov-24 |
||
Present to Council |
14-Nov-24 |
19-Dec-24 |
Conceptual Engineering |
November 14, 2024 – December 19, |
December 5, 2024 – |
2024 |
10-Jan-25 |
|
Prioritization + Refinements |
December 19, 2024 – January 23, 2025 |
January 10, 2025 – |
31-Jan-25 |
||
Draft Report |
4-Feb-25 |
21-Feb-25 |
Present to Council |
6-Feb-25 |
6-Mar-25 |
Final Report |
5-Mar-25 |
31-Mar-25 |
Estimate Project cost (Not to Exceed): |
$ 173,113.60 |
** This project is 100% funded by MSD.
Updated: November 19, 2024